Post-Construction Cleaning Bid Calculator

This page uses the same calculator to price a single project. Keep visits per week at 12/52: a month is 52 ÷ 12 weeks, so that is exactly one visit in the calculator's month, and the "monthly" bid price it shows is the price of the whole job. Enter a production rate that covers every pass combined.

Calculator

These starting rates are our own rough estimates, not an industry standard. Time your own crews and replace them. The post-construction starting rate here is 320 sq ft per labor hour. Pricing and bid-planning aid only, not financial, legal, medical or compliance advice.

1. The building

Interior floor area to be cleaned. Leave out exteriors, parking and any areas that are not in your scope.

Leave at 12/52 (about 0.2308) for a one-time job. A month is 52 ÷ 12 weeks, so 12/52 visits per week is exactly one visit in the calculator's month, and the monthly price shown is the job price. This is a workaround, not a schedule: change it only if you mean to price repeat visits.

2. Time and labor

How much one person cleans in an hour. Our own rough starting estimate for post-construction space is 320, not a standard: time your own crew and replace it.

What you pay per hour before payroll costs. Our $17 is a placeholder: use your own rate.

Payroll taxes, workers' comp and similar costs on top of wages. Our 20% is a placeholder, not advice: use your own figure.

3. Other costs

Chemicals, pads, liners and small tools, as a percentage of labor cost (wages plus burden).

Vehicle, phone, software, general liability insurance and admin, as a percentage of labor plus supplies plus extras. Do not count the same cost here and in burden.

Your cost for flat items on this job, such as renting a floor machine or a lift. The default of $150 is a placeholder. Enter your cost, not the customer price: overhead and margin are added on top.

4. Profit

Margin on price, not markup on cost. At 20%, a fifth of the price is profit after your costs. The results show the equal markup. Use 0 to see your break-even price.

A final clean after construction is not a recurring job. It is a one-time project, usually tied to a handover date, with layers of fine dust and residue that a regular janitorial visit never meets. The work tends to come in passes: a rough clean while the trades finish, a final clean before handover and a touch-up after the punch list. The condition of the building decides the hours, so two buildings with the same area can be very different bids.

What the starting numbers assume

About the production rate. Our starting estimate is 320 sq ft per labor hour for all passes combined, which is 25 hours for 8,000 sq ft. It is by far the slowest of our nine estimates, because of fine dust on every surface, labels and film to remove, and repeated passes. It is a rough guess of ours with no published source behind it. A building that was swept daily during the build may run much faster. One with heavy drywall dust, paint spatter or concrete residue can run much slower. Walk the actual site, time a sample room through every pass, and replace this figure.

These starting rates are our own rough estimates, not an industry standard. Time your own crews and replace them.

What to walk and measure

Before you quote post-construction space, walk it with a notepad and a stopwatch. Tick items off as you go.

Worked example: an 8,000 sq ft tenant build-out, one final clean

Picture an 8,000 sq ft commercial tenant build-out with an open work area, private offices, two restrooms and a kitchenette, cleaned as one project with all passes counted, and $150 of flat equipment cost. The calculator opens with exactly these numbers, and because it uses 12/52 visits per week (exactly one visit in the month), the "monthly" bid price is the price of the whole job.

Inputs: 8,000 sq ft, 12/52 visits per week, 320 sq ft per labor hour, an hourly wage of $17.00, 20% labor burden, 10% supplies, 12% overhead, $150.00 of extras for the job and a 20% profit margin on price.

  1. Hours for the job: 8,000 sq ft ÷ 320 sq ft per hour = 25.00 hours.
  2. Visits in the calculator's month: 12/52 visits per week × 52 ÷ 12 = 1.00 visit, so the whole job counts as exactly one visit.
  3. Labor hours for the job: 25.00 × 1.00 = 25.00 hours.
  4. Labor cost: wages of $425.00 plus 20% burden of $85.00 = $510.00.
  5. Supplies: 10% of labor cost = $51.00.
  6. Extras for the job, your cost: $150.00. Direct cost so far: $711.00.
  7. Overhead: 12% of direct cost = $85.32.
  8. Subtotal cost: $711.00 + $85.32 = $796.32.
  9. Bid price for the job: $796.32 ÷ (1 − 20%) = $796.32 ÷ 0.8 = $995.40. Of that, $199.08 is the profit built in.
  10. Price per sq ft for the job: $0.124. Revenue per labor hour: $39.82.

Shown numbers are rounded for display only. The calculator carries full precision, so adding up the rounded figures by hand can be off by a cent.

What if your own timing is 20% slower?

Suppose your timed walkthrough shows your crew cleans 20% fewer square feet per hour than our estimate: 256 instead of 320. Nothing else changes, and the bid price for the job becomes $1,191.75, which is $196.35 more, or $0.149 per sq ft. That is why you time your own crews instead of trusting a default.

Questions about pricing post-construction cleaning

How do I use a monthly calculator for a one-time clean?

The calculator multiplies visits per week by 52 and divides by 12 to get the visits in a month. At 12/52 visits per week (about 0.2308) that comes to exactly one visit, so the labor hours, costs and price it shows are for the whole job, not for a month. Do not change visits per week unless you mean to price repeat visits.

What production rate do I enter when a job has several passes?

Work from total hours. Time a representative room through every pass you plan, add the minutes, and divide the room's square feet by the total time in hours. Use that as the production rate. It is lower than the speed of any single pass, because it carries all of them.

What if the building is dirtier than I expected?

Say in the proposal what condition the price assumes and what happens if it is worse, for example an hourly rate for extra time. The "revenue per labor hour" result in the calculator is a handy floor for that hourly rate, because it is what your price already earns for each hour of labor.

Should I quote this job by the square foot?

Use price per square foot only as a cross-check against your own earlier jobs, and build the number from hours. Two buildings with the same area can differ a lot in dust, debris and fixtures. The per-square-foot figure here is the price of the whole job divided by the area, not a monthly figure.

How do I allow for a late handover or extra trade work?

The calculator has no contingency line. If delays could cost you crew time, put your own estimate of that cost as a flat figure in the extras field, or enter a slower production rate. Agree in the contract how a schedule change is paid for.

Other calculators

New to price per square foot? Read the guide to price per square foot, with worked examples from these calculators.

BidSheet is built and maintained by AI assistants working for Schlosser Studio, an AI-run studio owned by one person. It is not a staffed company and no human cleaning expert reviews your numbers.

A pricing and bid-planning aid only. It is not financial, legal, medical or compliance advice, and it makes no promise about earnings or about winning any bid.